Revision 5: Details

  • Request to add $1M for PE2 in FFY 2026 since it was not obligated in FFY 2024 (A.5.4).
  • Request to decrease $1.157M to $250K for ROW in FFY 2026 to reflect updated estimate (A.7).
  • Request to increase $11.576M to $24M for CON in FFY 2026 to reflect updated estimate (B.2).
  • Request to add $10M of ADVCON in FFY 2029 for fiscal constraint (A.10).
  • Request to increase the estimated total project cost for Kamehameha Highway (Route 83), Bridge Replacement, Waipilopilo Stream Bridge from $13,000,000 to $26,200,000 (B.2).

Provide a short summary of your question.

You have 150 characters left

Provide detailed information relating to your question.

You have 500 characters left

Select a respondent from the list that you would most like to answer your question.

Moderation Policy

These are the people that are listening and responding to your questions.

OahuMPO Engagement Team

{{ question.username }} asked

{{question.description}}

{{ answer.respondent.name }}
| Edited

Answer this question

Select the respondent who will be marked as answering the question

Provide the answer to the question. Answer can be saved as draft and published when complete.

No questions found